Contracting construction work typically involves either
the direct hiring of a contractor or competitive bidding
among different contractors. Government contracts differ
from nongovernment contracts in that private sector
contracts have few constraints, while public sector
contracts involve extensive regulations imposed by
the government.
Private sector construction contracts may either be
directly hired or bid upon. The direct hiring of a
contractor is the hiring of a contractor at the individual's
own discretion. Competitive bidding gives all contractors
a chance to bid on the construction contract and allows
the individual to hire the lowest bidder.
Public sector contracts must involve competitive bidding.
According to the Florida Supreme Court, since the government
is a major employer and is political in nature, there
is an assumption that there may be impropriety and
that the government cannot be trusted to meet and negotiate
suitable terms without at least the appearance of impropriety
or special favor. Thus, competitive bidding serves
the dual purpose of safeguarding against favoritism
toward a particular contractor and giving all a fair
opportunity to participate.
Contracting construction work typically involves either
the direct hiring of a contractor or competitive bidding
among different contractors. Government contracts differ
from nongovernment contracts in that private sector
contracts have few constraints, while public sector
contracts involve extensive regulations imposed by
the government.
Private sector construction contracts may either be
directly hired or bid upon. The direct hiring of a
contractor is the hiring of a contractor at the individual's
own discretion. Competitive bidding gives all contractors
a chance to bid on the construction contract and allows
the individual to hire the lowest bidder.
Public sector contracts must involve competitive bidding.
According to the Florida Supreme Court, since the government
is a major employer and is political in nature, there
is an assumption that there may be impropriety and
that the government cannot be trusted to meet and negotiate
suitable terms without at least the appearance of impropriety
or special favor. Thus, competitive bidding serves
the dual purpose of safeguarding against favoritism
toward a particular contractor and giving all a fair
opportunity to participate.
In most bidding procedures, there will be a request
for bids, which is an invitation to construction companies
to make bids on a construction project. (Private owners
and governments typically reserve the right to reject
all bidders, usually for skill or reputation in trade.)
After the request for bids, the bidders typically will
obtain bidding information, which includes the drawings
or plans for the project, job specifications, the parties
involved and the proposed contract. Upon receiving
the bid documents, the bidder will submit a bid proposal,
or the offer (usually irrevocable for a stipulated
time period). Factors considered in accepting a contractor's
bid include: financial ability, reputation, equipment
availability, skill and expertise. After the lowest
bidder's offer is accepted, the hirer (the owner or
public body) makes a formal award of the contract,
typically through written formal notification. If the
bidder signs the contract, a binding agreement is created.
Florida statutory law requires combative bidding, and
the Florida District Court of Appeals has held that
the government cannot split the contract into separate
pieces to avoid the statutory monetary minimum (with
exceptions for specialty work or work that requires
special skills not found in the general market). Further,
Florida courts have held that a public body may not
draw specifications in its bid request that would permit
only one bidder to qualify for the project.
Cases that involve fraud or ill repute in contract bidding
usually nullify the contract. For example, if a city
or county lacks the statutory authority to enter into
a particular contract, the contract is void and the
contractor may not recover for work performed. Cases
that involve bad faith or bribery are also nullified,
with the contractor receiving nothing.
However, accidental bidding discrepancies sometimes
occur. The nature of the bidding process means that
bidders sometimes miscalculate their bids. Florida
courts have granted relief when the mistake was an
honest error in mathematics or a clerical error but
have refused to grant relief for errors of judgment.
The Florida courts also have allowed rescission of
contracts when enforcement of the contract would be
unconscionable or when unforeseen circumstances render
the contract unenforceable. In cases of unconscionability,
courts will either grant relief to the bidder, a refund
of the bid deposit or an action for rescission of the
contract.
When the bidding contract involves a prime contractor
and a subcontractor, a subcontractor generally may
not hold the prime contractor liable for the prime
contractor's use of the subcontractor's bid unless
there was an agreement stating otherwise. Thus, if
a prime contractor uses a subcontractor's bid, the
prime is not compelled to use the subcontractor if
the prime is awarded the project; similarly, a prime
contractor may not hold a subcontractor liable for
the subcontractor's bid unless there was substantial
reliance on this bid by the prime contractor in making
his or her bid, in which case the court may impose
the doctrine of promissory estoppel and hold the subcontractor
liable for its bid.
There are three major methods of payment in construction
contracts: lump sum, cost-plus and unit price. Partial
payments are typically made to the contractor in incremental
sums during the project, with contract clauses usually
providing for a time or condition precedent for payment.
Lump sum payments are found in fixed-price contracts
and provide that upon completion of a contract, the
contractor is paid the amount due. Cost-plus contracts
provide that a contractor will be paid for all costs,
plus a percentage or fixed amount for profit and overhead.
The unit price method is used when the same project
will be completed several times, for example, a development
project where many houses are being built. A unit price
contract would provide a certain amount of houses and
a certain price per house, and the contractor would
be paid in increments upon the completion of each house.
Once the payment method is determined, the next step
is to calculate the terms and conditions for payment.
A relic of the English legal system under Oliver Cromwell,
performance contracts have typically required performance
of all labor before any payment is madeabsent an agreement
to the contrary. However, progress payments are instituted
in most construction contracts to provide relief to
ease the contractor's financial burden of having to
finance the entire projectincluding labor, supplies
and credituntil its full completion. Progress payments
are partial payments for work completed at a particular
stage of the project and ameliorate the problems of
payment collection.
In construction projects, performance may be less than
perfect and strict compliance with contractual provisions
may not be literal. In these cases, the Florida courts
have held that where there is substantial performance,
the contractor is entitled to recover the contract
price, less costs of remedying the minor defect or
omission or reimbursement for the diminished value.
In Florida, if the contractors have not substantially
performed their duties, then the contractor, under
a contractual restitution principle, may still recover
for work completed. Under this theory, the contractor
is paid the value of any benefit conferred upon the
owner by the contractor's performance.
Contractual undertakings require the implementation
of various clauses to protect owner, contractor and
subcontractor against ambiguities or contractual malfeasance.
Since there are as many standard construction contracts
as there are contractors and subcontractors, generalizations
concerning standard contracts can be perilously misleading.
However, the Association of General Contractors has
provided neutral contract provisions that construction
contracts should contain to prevent potential problems.
Unexpected delays or scheduling problems can require
last-minute modifications in the work assignments of
subcontractors and should be considered when forming
the contract. The Changes Clause allows for such delays
and is a standard in virtually every construction contract.
This clause allows changes to be made in the construction
of the project without completely stopping work on
the project altogether, and is normally construed to
require prompt performance on the part of the contractor
and subcontractor, with expedited consideration from
the owner because of any dispute involving the terms
of the change.
Before work on the project begins, each party should
be clear as to its duties and obligations, in other
words, the work and costs. This is contained in the
Scope of Work Clause, which defines the labor, materials,
services and costs involved in the project. Contractors
should be careful to avoid dragnet or all-inclusive
clauses with boilerplate terms like "all work
necessary to complete said project," "all
related items" and "all work normally undertaken
in this type of trade." Indeed, since the scope
of work is often defined in various documents, each
Scope of Work Clause should be identified and incorporated
as such into the general agreement.
Virtually all contracts contain a clause that allows
incorporation of a clause into the general agreement;
in construction contracts, these are typically called
Flow-Down and Flow-Up Clauses, also known as Conduit
Clauses.
A Flow-Down Clause provides that all duties and obligations
the contractor owes the owner are owed by the subcontractor
as well. Similarly, the Flow-Up Clause ensures the
owner's obligations and duties to the contractor will
also be owed to the subcontractor.
Parties should devote attention to Payment Clauses,
which set forth a schedule of payment that is contingent
on the general contractor getting paid before there
is any payment to the subcontractor, and Retention
Clauses, which stipulate that the subcontractor's work
must be satisfactorily completed before being paid
by the general contractor. Safety Clauses are often
standard and require subcontractors to observe basic
safety requirements on the job site. For projects involving
many subcontractors, Scheduling Clauses are often included
in each subcontract to ensure that neither party will
incur liability in the event that a third-party subcontractor's
performance is delayed.
Once the contract is executed, it may be modified only
if both parties mutually assent to the modification.
Agreement of both parties is required since the modification
is seen as a new contract, and therefore the contractual
requirements of offer, acceptance and consideration
(typically money or another benefit) apply. Florida
courts have stated that furnishing additional labor
and materials in exchange for more money is adequate
consideration. Written modifications are not required
unless the Statute of Frauds or the contract itself
necessitates a writing.
A frequent problem on construction projects is the discovery
of a previously concealed condition that makes the
work more difficult, more expensive or perhaps impossible
to perform. These discoveries typically result in a
need for additional time, contract revisions or even
rescission of the contract. Therefore, flexibility
to make changes is an important part of construction
law. Three types of clauses are used to deal with concealed
or changed conditions. First is the Site Investigation
Clause, which allows the contractor to make a claim
for any condition not reasonably discoverable by an
investigation of the site. Second is the Disclaimer
Clause, which expressly disclaims any responsibility
for site information given to the contractor. The third,
and by far the most common clause of this type, is
the Changed Conditions Clause.
There are two types of Changed Condition Clauses. The
first addresses the contractor encountering a condition
that is at variance with the conditions already documented
in the agreement; the second deals with the discovery
of conditions or situations that are anomalous or incongruous
with the type of work provided for in the contract.
In Changed Condition Clauses, custom in the trade is
often the standard for recovery, which is typically
allowed unless the contractor knew or should have known
of the conditions.
Most construction contracts involve time restraints
and many involve "time-is-of-the-essence"
provisions. However, delays in the completion of a
project sometimes happen, and a delay claim for damages
is essentially a claim that the contract has been breached.
In contract law, a breach of contract must be a material
breach to file a claim for damages. Tardiness in completion
alone is usually not part of the basic exchange of
values in a construction contract, and thus not a material
breach. Consequently, a construction contract should
specify whether damages are recoverable if one party
fails to perform.
Three kinds of clauses are generally used to ensure
indemnification in the event of a delay: Actual Damages
Clauses, Liquidated Damages Clauses and No-Damages-For-Delay
Clauses. Actual Damages Clauses provide that a delay
is a breach of the contract and that the breaching
party must pay money damages equal to the amount of
damages suffered. Liquidated Damages Clauses set an
agreed-upon amount for damages to be paid in the event
of a breach. No-Damages Clauses contractually limit
liability to provide no relief in the event of a delay.
Florida provides an interesting dilemma for subcontractors.
In a 1980 case involving a Liquidated Damages Clause,
the Court of Appeals held that a subcontractor may
be held liable for delay damageseven though other subcontractors
may contribute to the delayif the subcontractor's conduct
is a substantial factor in the project's delay.
A mechanic's lien is a security device by which unpaid
contractors, subcontractors and suppliers may enforce
payment for services and materials through the lien
process. To acquire a mechanic's lien, a claimant must
fall into one of the designated classes of lienors
expressly created under Florida Statute $713, including:
contractors, subcontractors, suppliers, laborers and
mechanics. Mechanic's liens are typically statutory,
so claimants must observe the regulations in strict
obeisance. Substantial performance and proof of use
of the materials into the construction project are
required before the lien will attach. In Florida, evidence
that materials were delivered to the site is sufficient
proof that materials were used in the construction
project. However, once a lien is attached to the property,
the courts will liberally interpret the lien requirements
in order to accomplish the parties' objectives in completion
of the project. In the event that the parties' objectives
(presumably, completion of the project) cannot be met,
Florida courts have allowed the claimant to use the
remedy of repossession. Proceedings for repossession
are quite similar to proceedings used to foreclose
a mortgage, and are subject to time constraints imposed
by either the mechanic's lien statute itself, or by
the statute of limitations.
Defenses to mechanic's liens are found in Florida case
and statutory law. An owner may defeat a claim for
a mechanic's lien by proving lienor's failure to comply
with the statutory requirements or fraudulent conduct,
or contractual provisions showing waiver of the lien
or lien preclusionprovided the language of the waiver
or preclusion is clear and unambiguous. Further, if
the holder of the lien gave false, misleading or inflated
price information, any mechanic's lien will be rendered
null and void. Florida's lien statute ($713.29) provides
that the prevailing party in a mechanic's lien foreclosure
will recover reasonable attorney's fees in an amount
to be determined by the court.
Typically, owners will require the contractor to provide
the owner with a private payment bond. Private payment
bonds protect the owner from mechanic's liens from
various subcontractors in the event of their nonpayment
by the contractor. The bond's surety either will pay
to the extent of the amount specified in the bondprovided
the claimant furnishes the requisite notices to the
debtoror will effect performance of the work.
Finance creativity in construction projects has resulted
in lenders becoming more involved in the construction
process, thus expanding the boundaries of lender liability.
Developers who wish to obtain a construction loan typically
need to present a loan commitment to the construction
lender for approval. Upon approval of the loan, the
relevant parties agree that when the construction project
is completed, the permanent lender (the owner's bank)
thereupon will purchase the construction loan from
the construction lender (typically a commercial bank
that specializes in short-term construction loans).
When lenders participate with developers in joint ventures,
Florida courts have consistently found lenders liable
to third-party purchasers for construction defects.
In Florida, a joint venture exists if four elements
are found: (1) a common purpose, (2) joint control
or right of control, (3) joint proprietary interest,
and (4) mutual sharing of profits and losses. If the
existence of each element is proven by the claimant,
the lender will be liable to third-party purchasers
for construction defects.
Most courts do not hold lenders liable for negligence
claims on construction projects, and Florida is no
exception. Construction lenders periodically may inspect
the site to monitor project progress, and often extract
a fee for doing so. Florida courts have held that even
if an inspection fee is extracted from the construction
loan, this does not give rise to the requisite duty
standard required for a negligence action. However,
if the lender assumes title of the project or becomes
more than a lender by holding itself out to be the
developer or owner to purchasers, the lender will then
be held liable for completion of the project to the
extent of the express representations made to the buyer.
Further, the assuming lender may be liable for construction
defects and breach of any warranties due to these defects.
In large construction projects (and some smaller jobs),
design professionals such as architects or engineers
provide blueprints and plans for more sophisticated
design projects like condominiums, office buildings,
shopping malls or even homes. Although form agreements
in construction contracts have become customary, ignorance
of their legal significance can be very problematic
for contractors and design professionals. If design
professionals fail to perform their duties properly,
they can be held liable for breach of contract, negligence,
failure to disclose a material or latent defect, or
other actions if the court finds their conduct subjects
the architect or engineer to strict liability.
The construction contract lists the duties of the design
professionals, and if these professionals fail to perform
their duties, the owner may sue for breach of contract.
Damages for breach are limited to an amount that is
reasonably foreseeable at the time the contract was
made or to an amount that is a natural consequence
of the breach.
Design professionals acting in their professional capacity
are held to a higher standard of care that is consistent
with their higher degree of knowledge and skill. Therefore,
a design professional whose performance does not meet
the reasonable standard of care of similar professionals
with similar skills will be found liable for negligence.
This negligence standard applies to the professional's
drawings or plans, preparation, inspections and supervision
of relevant personnel. If it is reasonably foreseeable
that the negligent conduct will result in injury and
the design professional may be liable to third parties
for sustained injuries. However, negligence claims
or tort actions generally do not allow recovery for
solely economic losses. To recover economic losses
in a tort action, the design professional must be held
liable under a standard called strict liability.
Strict liability is a tort concept in which one is found
liable regardless of fault, contributory negligence
or anything else that normally absolves persons of
liability. Courts have been reluctant to impose strict
liability on design professionals as it is usually
impossible to differentiate between a construction
defect and a design defect because they are often closely
intertwined.
However, none of these standards of liability are designed
to assure conformity with the plans or specifications
by the design professional. No construction contract
guarantees or implies perfection in either plans or
results, and design professionalsabsent strict liabilityare
liable only for failure to exercise reasonable skill
in preparation and execution of the plans. Similarly,
contractors are not responsible for defects in the
plans or specifications given to them by design professionals
hired as independent contractors.
Design professionals may need to hire consultants from
various disciplines for construction projects. Consultants
such as structural, civil or mechanical engineers or
electrical experts working on construction projects
at the behest of the architect or engineer (as opposed
to being hired by the owner) are considered independent
contractors. According to the federal courts and Restatement
(Second) of Agency, $220, in determining whether a
consultant is an independent contractor or an employee
the court will consider: the extent of control that
the design professional may exercise over the details
of the work; the terms of the agreement; the method
of payment; the degree of skill required for the job;
previous dealings between the parties; and previous
scopes of employment of the consultant. If the relationship
is determined to be employer/employee, then the tort
doctrine of respondeat superior applies, making the
employer responsible for the torts committed by the
employee (if committed within the scope of employment).
A design professional acting as an independent contractor
is generally not liable for the acts of the independent
contractor, since the duties were delegated to this
contractor in a consultant capacity. However, sometimes
ordinances or building codes will create non-delegable
duties of compliance, such as fire codes regulating
a project's design. In these cases, independent contractors
may be liable for injuries sustained by those within
the class of people intended to be protected by the
ordinance.
Construction agreements commonly provide details on
who is responsible for bearing the responsibility for
accidents on the site. Florida Statutory law requires
comprehensive general liability insurance ($489.115)
and workers' compensation insurance ($440 et. seq.).
Builder's risk insurance and professional liability
insurance are standard in most construction contracts.
Most contracts contain indemnity provisions to determine
who will bear the risk of loss should an on-site accident
occur, and the purchaser of the insurance should be
required to furnish a copy of the policy to the other
party.
Comprehensive General Liability Insurance protects contractors
against claims brought against them because of occurrences
in privity with the contractor's work, and coverage
typically extends only to property damage and bodily
injury. Business risks such as claims for defective
work or structure defects are covered by other policies;
builder's risk insurance protects against loss to buildings
during construction, alteration or repair. (This coverage
is usually voided once the work is done or once the
project is occupied.) Professional liability insurance
is carried by professional designers to protect against
losses relating to their work on the project or to
cover claims made against them by third parties. Although
Florida law does not require professional liability
insurance, owners are increasingly requiring design
professionals to carry it since owners may have a claim
against the design professional for losses relating
to the project or for satisfaction of claims to third
parties.
Usually a Comprehensive General Liability Insurance
policy excludes coverage for workers' compensation
claims, unemployment compensation or disability benefits.
This risk insurance is obtained under separate policies
and in every state, workers' compensation coverage
is required for all employers. In Florida, general
contractors are typically required to procure workers'
compensation for subcontractors as well as employees.
However, it is customary for general contractors to
fulfill this duty by requiring their subcontractors
to procure the coverage themselves. If subcontractors
do not obtain this coverage, despite their obligation,
the general contractor is still responsible to procure
this insurance coverage. In this event, Florida courts
have allowed contractors to file a claim against the
subcontractor for any damage or increased premiums
caused by the subcontractor's failure to procure workers'
compensation coverage. In contrast, the contractor
is generally not obligated to provide coverage for
vendors or lessors of equipment. Further, if the worker
is an independent contractor instead of a subcontractor,
general contractors are not obligated to provide workers'
compensation coverage. Florida courts use a two-pronged
test to determine whether the worker is a subcontractor
or an independent contractor: 1) Is there a subletting
of the contractor's work? and 2) Does the contractor
have control over the worker? If an employee files
a workers' compensation claim and wins, then that is
the sole recovery for the employee. However, it is
possible under certain conditions that an independent
contractor may file a separate claim against an employee
or subcontractor on the site.
Breach of construction contracts entails many things:
the owner's failing to make periodic payments, failure
to cooperate by either party, unforeseen conditions
that render completion impractical or impossible, project
abandonment or a general failure to fulfill the contractual
obligations. If conditions occur that make performance
by one party impossible, then a party not at fault
may, in good faith, terminate the contract for cause
without fear of damages. However, these terminations
must not be arbitrary or unreasonable or they will
constitute wrongful termination. Wrongful termination
is a breach of contract for which the injured party
may collect compensatory damages, which typically amount
to lost profits and a reasonable calculation of labor
and materials involved in the partial completion of
the project.
Most construction contracts contain either a Time-Is-Of-The-Essence
Clause, a Damages-For-Delay Clause or a No-Damages-For-Delay
Clause. These clauses typically insulate, protect or
prevent one of the parties from having to breach the
contract in the event of nonperformances, such as unforeseen
circumstances or impractical occurrences. More importantly,
they provide remedies, or a limitation of remedies,
in the event of a breach. A Time-Is-Of-The-Essence
Clause will provide a fixed time for performance, with
a remedy if completion exceeds this time allotment.
A Damages-For-Delay Clause provides remedies for the
contractor in the event of noncooperation from the
owner, or contingencies that interfere with a timely
performance. No-Damages-For-Delay Clauses protect the
owner from breach assessments in the event of certain
listed occurrences, such as financing problems or construction
access easements. This clause will exclude damages
against the owner for delay of performance.
Introduction to Construction Law, Steven M. Siegfried,
ALI/ABA Continuing Legal Education, Philadelphia, PA
(1987).
Handbook of Modern Construction Law, Jeremiah D. Lambert
and Lawrence White, Prentice-Hall, Inc., Englewood
Cliffs, NJ (1982).